'''23-Jan-2005'''
 
'''23-Jan-2005'''
* Revision of the VLAN schedule, primary aim to assign private IPs to most of our systems
+
* Revision of the VLAN schedule, primary aim to assign private IPs to most of our systems especially the Research Labs.
  
 
'''31-May-2005'''
 
'''31-May-2005'''

Revision as of 16:48, 12 January 2006

This page describes (or connects to) one or two current activities for each group.

Labs and Students Support Group

Until January 20:

  1. Install Printer HP2200 to Graduate Lab 201(hp1-201 ?). Done 11/01/2006
  2. Install Opnet Application Capture Agents to 201 lab ???
  3. Prepare new programm for epithrhtes.
  4. Clear local profiles from all lab machines.
  5. Order maintenance kit for HP1-B123 and HP1-L0.
  6. Prepare and place new PCs (Fujitsu Siemens) for 201. (How many???)
  7. Set bios passwords for administrator and also user (not to get mac addresses). not possible
  8. Check all DLP`s in labs.
  9. Deny access to domain users to command "getmac". Done 11/01/2006
  10. Stop sychronization by some users to Windows machines (sychronize only when they are logging off - NOT always).
  11. Find a way to change SID to each PC. ???
  12. Prepare and replace 4 w/s at B103 tm 14:53, 12 Ιαν 2006 (EET)


Until May 31:

  1. Prepare installation images for lab B101


Until August 31:


Core Systems Group

Until January 20:

  1. Install Print Manager Plus s/w?? or postponed it for next semester

Until May 31:

  1. TSM
    • Install 2 HDD
    • Reconfiguration of policies
    • Include new ultirum drive in set-up
  2. Prepare a "new Electra" with IIS etc
  3. Format Electra
  4. Prepare a new Astarti
  5. Format and prepare Astarti
  6. Review and remove old students,faculty,research a/cs
  7. Finish with TrendMicro server set-up - resolve some problems
  8. Prepare and finalize Server Storage Plan

Networks and Security Group

23-Jan-2005

  • Revision of the VLAN schedule, primary aim to assign private IPs to most of our systems especially the Research Labs.

31-May-2005


31-Aug-2005