This page describes (or connects to) one or two current activities for each group.

Labs and Students Support Group

Until January 20:

  1. Install Printer HP2200 to Graduate Lab 201(hp1-201 ?) Done 11/01/2006
  2. Install Opnet Application Capture Agents to 201 lab ??? postponed until next semester
  3. Prepare new programm for epithrhtes
  4. Clear local profiles from all lab machines
  5. Order maintenance kit for HP1-B123 and HP1-L0
  6. Prepare and place 4 new PCs (Fujitsu Siemens) for B101 Done 19/01/2006
  7. Set bios passwords for administrator and also user (not to get mac addresses) not possible
  8. Check all DLP`s in labs.
  9. Deny access to domain users to command "getmac" Done 11/01/2006
  10. Stop sychronization by some users to Windows machines (sychronize only when they are logging off - NOT always)
  11. Find a way to change SID to each PC ??? time-consuming and not really necessary since machines will be reformatted next semester
  12. Prepare and replace 4 w/s at B103 tm 14:53, 12 Ιαν 2006 (EET)
  13. Replace Norton Anti-virus on CS1993 (room 148) Done 16/01/2006


Until May 31:

  1. Order USB extensions for lab B101 (Fujitsu Siemens PCs)
  2. Prepare installation images for lab B103
  3. Update Computing site
  4. Update Helpdesk site
  5. MSDNAA
  6. Update print guide to include print quotas
  7. Investigate the problem with standby mode on IBM machines
  8. Order process (CRM???)
  9. Prepare and place 4 new PCs (Fujitsu Siemens) for 101. Done 02/02/2006
  10. Find a solution to Acrobat Distiller 7.0 CPU usage problem.kekkos
  11. Find a solution to jedit (B121-B123) problem.


Until August 31:

  1. Apply images for lab B101.
  2. Update all labs softwares.


Core Systems Group

Until January 20:

  1. Install Print Manager Plus s/w?? or postponed it for next semester

Until May 31:

  1. TSM
    • Install 2 HDD (Tuesday Feb. 15)
    • Reconfiguration of policies
    • Include new ultirum drive in set-up
  2. Prepare a "new Electra" with IIS etc
  3. Format Electra
  4. Set an internal MYSQL server and move all DBs on it
  5. Prepare a new Astarti (www2n)
  6. Move most if not all of www2 to www2n
  7. Format and prepare Astarti
  8. Review and remove old students,faculty,research a/cs
  9. Finish with TrendMicro server set-up - resolve some problems
  10. Prepare and finalize Server Storage Plan
  11. DHCP and DNS server upgrade

Networks and Security Group

23-Jan-2005

  • Revision of the VLAN schedule, primary aim to assign private IPs to most of our systems especially the Research Labs.

31-May-2005

  • Wireless network - phase 1
  • Properly install and test accees points as they are now without any AA scheme or OS upgrade - good old open way
  • Test - proper network access, XWIN, printing, E-mail etc.
  • Wireless network - phase 2
  • Upgrade all access points we use to IOS software
  • Decide on the best AA scheme and see that is implimented in a minimum configuration
Radius server running is a must for this phase with NIS capabilities
  • Wireless network - phase 3
  • See if we can put these access points in a dual VLAN mode so that they work for both the newcampus and zephyros SSID
  • Make Radius authenticate via the LDAP server and/or NIS


31-Aug-2005